2023/10/14Return visit of 10000 liquid ASU project
Recently, our company's technical leader came to the site of the 10000 liquid air separation project for a return visit and had a careful and detailed understanding of the equipment production of
Learn More >
2023/09/12215,000 Nm3 oxygen air separation units have been started up complete successfully
Kylin's leading product air separation equipment has formed a series of 1500-60000Nm3/h and has the ability to manufacture air separation equipment of 100000 levels. Recently, Kylin's two
Learn More >
2023/07/0490,000 t/a LNG project —— completion of LNG cold box machinery
LNG cryogenic cold box is a heat exchange equipment used to realize heat exchange between raw natural gas and refrigerant.
Learn More >
2021/04/27Awarded as "Henan Province Energy-saving Air Separation Plant Engineering Technology Research Center...
Henan Kaiyuan Air Separation Group Co., Ltd. strives to build a high-level innovation platform. In February 2021, the R&D Department of Kaiyuan Air Separation Group was approved as "Henan Province Energy-saving Air Separation Plant Engineering Technology Research Center".
Learn More >
2021/03/25Qinghai Hongyuan Gas 8200 air separation project was put into operation
On March 20, 2021, through the joint efforts of all the contractors all staff, by my company for the qinghai hongyuan gas co., LTD., provide KDONAr - 8200/14000/280 type air separation unit smoo
Learn More >
2020/07/22A New Achievement to Boost Development
The fins, deflectors, and seals are placed between two adjacent plates to form an interlayer. Such interlayers are overlaid in different ways based on the fluid and brazed into a whole to form a plate bundle.
Learn More >
2020/07/16Linked Trial Run of 25,000 m3/h Air Separation Project in Anhui Succeeds
The Company undertakes the construction of the Anhui 25,000 nm3/h air separation project. With the close cooperation and unremitting efforts of design, manufacturing, and installation departments for over more than 7 months, the ASU was successfully put into production at its first trail run on Octo...
Learn More >
2020/05/19Commissioning of 42000 Air Separation Unit Exported to Indonesia Will be Conducted
The single machine commissioning, exposed cooling experiment and pearlite filling of our KDONAr-42000/42000/1200 ASU in Indonesia which is built for the OSS Stainless Steel Integrated Project with an annual output of 3 million tons, have been completed with the joint efforts and cooperation.